|
The
Clock Is Ticking
November, 2002
More than the Columbia River separates Oregon from our
neighbors to the North. That is nowhere more apparent than
in comparing the statutes of limitation and ultimate
repose for Oregon and Washington in the area of
construction defect litigation, where so many of us seem
to be preoccupied in recent years. The purpose of this
article is not to provide a detailed comparison of Oregon
and Washington law, but instead to provide a general
framework for analysis of whether a statute of limitations
has run on a construction defect claim arising in either
state.
Before we explore the differences between Oregon’s and
Washington’s unique treatment of the timelines for filing
claims, let us look briefly at the distinction between a
statute of repose and a statute of limitations.
Statute of
Repose
A statute of repose is an “overall maximum” time limit in
which a lawsuit must be filed. Al Disdero Lumber Co. v.
Dick W. Ebeling, Inc., 95 Or. App. 671, 674, 770 P.2d
945 (1989). “It starts to run from delivery of a product
or completion of work and cannot be extended, regardless
of any unfairness to a plaintiff.” Id. Generally,
statutes of repose are not concerned with when a plaintiff
learns he or she has a claim. Id. In the construction
context, the day the statute of repose begins to run is
usually the date a certificate of occupancy is issued by
the county building official.
Statute of
Limitations
In contrast, statutes of limitation are the maximum time a
person is allowed to file his or her claim after the claim
has “accrued,” limited only by the relevant statutes of
repose. A claim generally “accrues” when a person knows
that he or she can sue another. Berry v. Branner,
245 Or. 307, 311, 421 P.2d 996 (1966). Unlike statutes of
repose, statutes of limitation are not necessarily tied to
the date the product was delivered or the work performed.
Al Disdero Lumber, 95 Or. App. at 674. As an
example, if a house was built and a certificate of
occupancy was issued on January 1, 2000, the statute of
repose began to run on that date. If the roof began to
leak on September 15, 2002, then that is the date on which
the claim “accrued,” and the date on which the statute
of limitations began to run. Generally, a statute of
limitations never extends beyond the outer limit of a
statute of repose, but the Washington statute of repose
does not follow that model, as explained below.
The Oregon
Model
Oregon’s statutes of repose and limitation are relatively
straight forward and need little interpretation. The
statute of repose governing claims arising out of the
construction of improvements on real property is found in
ORS 12.135(1). It requires all construction defect claims
to be filed with the court within 10 years from the date
of substantial completion or abandonment of the
construction project, no matter when the claim accrues.
The statute of limitations is determined by the nature of
the claim. Oregon recognizes claims for negligent
construction. See Newman v. Tualatin Development Co.,
Inc., 287 Or. 47, 52, 597 P.2d 800 (1979). Claims for
negligent damage to property must be filed within 6 years
from the date a claim accrues (ORS 12.080(3)), unless the
claim is against an architect, landscape architect or
engineer, in which case the claim must be brought within 2
years from the date the damage is discovered (ORS
12.135(2)). In negligence claims, Oregon courts have
adopted a “discovery rule,” meaning that the claim accrues
(and the clock starts to tick) when all the facts
necessary to assert a claim become known, or should have
become known, to the plaintiff. Accordingly, if a
plaintiff discovers a claim, he or she has 6 years in
which to file a lawsuit, provided the filing occurs no
later than 10 years from the date of substantial
completion. As an example, if plaintiff discovers the
defect 9 years after substantial completion, he or she
will only have 1 year to file a lawsuit because the claim
must be filed within the 10-year statute of repose.
Claims arising from breach of a construction contract,
whether written or oral, must also be brought within 6
years from the date of the breach, and no later than 10
years from the date of substantial completion. See ORS
12.080(1) and Ass’n of Unit Owners of the Inn at Otter
Crest v. Far West Fed. Bank, 120 Or. App. 125, 134,
852 P.2d 218 (1993).
Some states also apply the “discovery rule” to determine
when a claim accrues in a breach of contract case.
Remember that pursuant to the discovery rule, the statute
of limitation is not triggered until the date of discovery
(as opposed to the earlier date of the breach). Again, ORS
12.135(2) expressly applies the discovery rules to claims
against architects, landscape architects and engineers.
ORS 12.080(1), the statute of limitations for all other
contract claims has no such language. However, the Courts
have implied that the language of ORS 12.010, the statute
governing the time for commencing actions, operates as a
discovery rule. While no Oregon court has expressly held
that the “discovery rule” applies to breach of contract
cases, it is likely they would apply the discovery rule if
faced with that particular question.
The Washington
Model
Just when you thought you had a clear understanding of how
statutes of repose and limitations compliment one another,
welcome to the Evergreen State. The good news is that
Washington courts do not recognize claims for negligent
construction. Further, it is not yet clear whether
Washington courts will recognize claims for equitable
indemnity, as the courts have previously determined that
these types of claims are based on negligence. While other
types of construction-based claims do exist (e.g., breach
of warranty, and contractual indemnity), most Washington
construction defect cases are essentially breach of
contract claims. Whether the contract is oral or written
is important in determining which statute of limitations
to apply. How many times have you asked your subcontractor
insured for a copy of his contract with the general, only
to be told “what contract? We did everything on a
handshake.” The answer to this question is important
because there is a 3-year statute of limitations for oral
contracts, and a 6-year statute of limitations for written
contracts.
In order to properly apply the statutes of limitation and
repose to Washington construction defect claims, a
two-step analysis is required. Washington now applies the
“discovery rule” to breach of contract claims between
building owners and general contractors.
Architechtonics Construction Mgmt, Inc. v. Khorram,
111 Wash. App. 725, 727-28, 45 P.3d 1142, 1144 (2002).
“The statute of limitation for contract actions begins to
run when a party knows or, in the exercise of due
diligence should know, of the other party's breach.” Id.
at 737. The discovery rule in construction cases is
limited, however, by Washington’s construction statute of
repose. This is where Washington parts company with Oregon
in defining the statute of repose as the “overall maximum”
time limit for filing a claim.
Washington’s construction statute of repose, RCW 4.16.310,
requires all claims brought on a contract for the
construction of a building to have “accrued” within 6
years from the date of substantial completion. The date a
claim accrues is the date the defect is discovered.
Architectonics, 111 Wash. App. at 737. If a
homeowner does not discover a defect within 6 years
of substantial completion, he or she is simply out of
luck. Substantial completion may be determined by the date
a certificate of occupancy is issued (see
1519-1525 Lakeview Blvd. Condo. Ass’n v. Apartment Sales
Corp., 101 Wash. App. 923, 932, 6 p.3d 74 (2000)) or
the last day a contractor performed work on the job,
whichever is later. See Parkridge Assoc. Ltd. v.
Ledcor Ind., Inc., et al, No. 48337-4-1, 54 P.3d 225,
2002 WL 31105482, *3 (Wash. App. Div. 1)(see further
discussion of Parkridge herein regarding its effect
on indemnity claims). In other words, if, according to the
certificate of occupancy, a residence is substantially
complete on January 1, 2000, then claims against the
contractor for breach of a written construction contract
must accrue (be “discovered”) on or before January 1,
2006. If the owner does not discover the defect until
January 2, 2006, the statute of repose bars the claim
forever.
If a homeowner does discover a defect within 6 years
following substantial completion (the “repose” period), he
or she then has the applicable statute of limitations
period in which to bring a claim against the general
contractor. This could potentially extend the statute of
limitations for filing a claim well beyond the 6-year
statute of repose. Again, the statute of limitations on a
written contract is 6 years from the date the
breach is discovered (RCW 4.16.040(1)) and 3 years from
the date of the breach of an oral contract (RCW
4.16.080(3)). Because Washington’s statute of repose
provides a 6-year limit on when the claim must “accrue,”
the total period of time to bring a claim on a written
contract could be as long as 12 years. In other words, if
substantial completion of the project is January 1, 2000,
and the owner discovers the defect on January 1, 2006,
(within the 6 year statute of repose) he or she still has
6 additional years from January 1, 2006, in which to file
his or her complaint on the written contract. If the claim
arises from an oral contract, the owner has 3 additional
years from the date of discovery of the defect to bring a
claim, or a total of 9 years.
Similarly, if a defect is discovered early on, within the
6-year statute of repose, the lawsuit must be filed within
6 years (written contract) or 3 years (oral contract) from
the date of discovery. For example, if substantial
completion of an oral contract occurs on January 1, 2000,
and the homeowner discovers the defect on January 1, 2001,
he or she must file the suit no later than January 1,
2004, which is less than the 6-year statute of
repose. Confusing? Yes. Important to know? Absolutely! If
you handle Washington claims, you need to be aware of
Washington’s statute of repose and its unique application.
On a related subject, on September 23, 2002, the
Washington Court of Appeals threw a new wrench into the
mechanism for defending construction defect claims. In the
Parkridge case, the court held that the typical
contractual indemnity claim between a general contractor
and subcontractor must also accrue within the 6-year
construction statute of repose. 2002 WL 31105482 at *5-*6.
This, in effect, requires a general contractor to sue
subcontractors within 6 years following substantial
completion (the “statute of repose” window), even though
the general contractor may not have become aware of the
underlying claim from the homeowner until a few days
before the 6-year period of repose expires. In light of
the Parkridge decision, general contractors run a
very high risk of losing their opportunity to sue
subcontractors for contractual indemnity in cases where
the general is sued by the homeowner on the eve of the
expiration of the statute of repose.
If you have any questions, please feel free to contact the
author, Martin M. Rall, by phone at
(503) 768-9600, or email at
marty@lerlaw.com.
©
1999 - 2004 Lachenmeier Enloe Rall & Heinson
|